Had one can anticipate what we would expect 11 months after signature of the contract with the company IBGHAUS, you would probably have clearly decided against building a house with this company. Unfortunately we had little information about us could be expected customer treatment by IBGHAUS.Wir not imagine that such ignorance on the part of IBGHAUS's management is practiced. Our impression, after signing the purchase contract, we were graded by the customer to the petitioners. Our letter to the Board in Büdelsdorf / Central or Hennigsdorf were not answered in the first few months. Initial emphasis and brought several reminders.
movement in our resulting IBG ruin. We will provide the Bauprotokoll created by us in the next few weeks in detail to the internet and add further images.
We call witnesses.
also written and verbal demands and judgments of our privately commissioned, state-chartered building surveyor, Mr S, were ignored by IBG.
We now have a house in the middle of winter with no insulation and plaster, is solely the fault of IBG house.
The house has, according to advertisement of IBGHaus a construction period of up to 5 months, this meant the sales manager Mr OR, if it was still a lot of air. He expected four-month construction period.
Here is the catalog offered in IBGHAUS AVANTGARDE HOUSE see and which is now a reality.
The house has been scheduled in early December, then we could not detect any further activity. We suspect that this will now be hidden for almost 10 months of continuous Baudrama now.
If you want to direct your questions and comments to me, please use the comment function of my blog or send me an E-mail: domingoboot@gmail.com